上部结构左幅设计为(2×30m+3×30m+(30m+30.325m+30m))现浇连续箱梁+三跨悬臂梁+((25.675m+30m+30m)+3×30m+3×30m)现浇连续箱梁,右幅设计为(2×30m+3×30m+(30m+30m+25.675m))现浇连续箱梁+三跨悬臂梁+((30m+30.325m+30m)+3×30m+3×30m)现浇连续箱梁。现浇箱梁设计为预应力混凝土连续箱梁,每幅桥为6联,全长506米。箱梁中线处设计梁高为1.6m,单箱三室。现浇箱梁施工采用支架法施工,支架全部采用碗扣式脚手架和工字钢梁。箱梁外侧模板、底模均采用竹胶板,内模采用木模板,砼采用砼运输车、砼输送泵分成两次浇筑成型的方法。